Criteria Development
Important deadlines for acceptance criteria going to the Evaluation Committee hearing
The deadlines noted below will be used by ICC-ES staff in preparing acceptance criteria for upcoming meetings. For acceptance criteria to be placed on the agenda, the proposed criteria must, in the opinion of ICC-ES, either be ready for approval by the Evaluation Committee, or be in need of input from the Committee and industry so that staff can make needed changes and bring it back for approval at a future meeting. For staff to meet these deadlines, and to ensure that items have received adequate technical development and review, proponents of acceptance criteria must themselves meet certain deadlines. The deadline for a proponent to provide ICC-ES staff with a working draft of a criteria, and applicable supporting data, is nine weeks prior to the date the criteria is posted for public review.
For June 5–6, 2013 Updated click here
For October 15–17, 2013 click here
June 5–6, 2013
Sheraton Gateway Hotel Los Angeles, Los Angeles, California
| PROCESSING OF ACCEPTANCE CRITERIA |
| February 22, 2013 Criteria proposals must be forwarded to staff |
| March 15, 2013 Staff must have the criteria draft prepared for internal review |
| April 25, 2013 Staff e-mails notice of committee meeting to public |
| April 25, 2013 Staff posts criteria on web site for public review |
| May 16, 2013 Public comments due to ICC-ES |
| May 31, 2013 Staff posts memos to Evaluation Committee on web site |
October 15 - 17, 2013
DoubleTree Hotel, Birmingham, AL
| PROCESSING OF ACCEPTANCE CRITERIA |
| June 21, 2013 Criteria proposals must be forwarded to staff |
| July 19, 2013 Staff must have the criteria draft prepared for internal review |
| August 28, 2013 Staff e-mails notice of committee meeting to public |
| August 28, 2013 Staff posts criteria on web site for public review |
| September 18, 2013 Public comments due to ICC-ES |
| October 11, 2013 Staff posts memos to Evaluation Committee on web site |